Jal Jeevan Mission (JJM)-5th SLSSC - Laying dist: system and providing 1593 FHTCs from proposed OHSR at Malappuram in Thumpamon panchayath.-.-Pipeline Work

Project Jal Jeevan Mission (JJM)-5th SLSSC - Laying dist: system and providing 1593 FHTCs from proposed OHSR at Malappuram in Thumpamon panchayath.-.-Pipeline Work
Project Code PTAJJM022214292
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-5th SLSSC - Laying dist: system and providing 1593 FHTCs from proposed OHSR at Malappuram in Thumpamon panchayath.-.-Pipeline Work
Status On-going
District Pathanamthitta
Executing Office Pathanamthitta Sn
AS Amount (Rs) 391100000
AS Number GO(Rt) /134/2022/WRD
TS Amount (Rs) 81700000
TS Number TS/13168/2022_26_1_1
Total Bill Submitted (Rs) 1553654
Total Bill Paid (Rs)
Population Benefitted 30000
Capacity in MLD 1.00
Actual Project Completion Date 12 Oct 2023
Coverage Thumpamon Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-5th SLSSC - Laying dist: system and providing 1593 FHTCs from proposed OHSR at Malappuram in Thumpamon panchayath.-.-Pipeline Work Pathanamthitta Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Apr 2024 work in progress Pathanamthitta PH Section - AE
01 Dec 2023 Work in progress, 12% of work completed Pathanamthitta PH Section - AE
17 Jun 2023 Work in progress, 2% of work completed Pathanamthitta PH Section - AE
16 Jun 2023 Work in progress, 2% of work completed Pathanamthitta PH Section - AE
15 Jun 2023 Work in progress, 2% of work completed. 90mm PVC pipe - 60m laid, 20mm PVC 81m laid Pathanamthitta PH Section - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/04/2023
Scheduled date of Completion of the Project 12 Oct 2023
Expected date of Completion 30/01/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 24 Jan 2023

Other details

Project Officers View