Project | Deposit Work - 2021-22 - Annual project of Kumbalanghy panchayath - Urgent maintenance and strengthening of Kumbhalanghy pump house |
---|---|
Project Code | EKMGOK02218394P1 |
Type | Package |
Main Project | Deposit Work - 2021-22 - Annual project of Kumbalanghy panchayath - Urgent maintenance and strengthening of Kumbhalanghy pump house |
Funding Agency | GOK |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Deposit Work - 2021-22 - Annual project of Kumbalanghy panchayath - Urgent maintenance and strengthening of Kumbhalanghy pump house |
Status | On-going |
District | Ernakulam |
Executing Office | Karuvelippady Sn 3 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 1000000 |
TS Number | TS/2021-2022/2021/12849 |
Technical specification | Deposit Work - 2021-22 - Annual project of Kumbalanghy panchayath - Urgent maintenance and strengthening of Kumbhalanghy pump house |
Contractor | Akhilesh.E.P (Mob: 9946413213) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 01 Mar 2022 |
Expected date of Completion | 31/03/2022 |
TS Date | 29 Jun 2021 |
---|---|
Estimate Approval | 01 Jul 2021 |
NIT Approval | 29 Sep 2021 |
Tender Closing | 18 Oct 2021 |
Technichal Pre-Qualification | 19 Nov 2021 |
Price bid opening | 24 Nov 2021 |
Workorder Date | 24 Nov 2021 |
---|---|
NA | 30 Nov 2021 |
Karuvelippady AEE |
Date: 06/10/2022 |
Work has been completed | 100% Completed
Bill Submitted to Division office.
Karuvelippady AEE |
Date: 03/10/2022 |
Work has been completed | 100% Completed
Bill under scrutiny in Sub Division .