State Plan - BAWSS to Kundara and adjoining panchayats-Replacement of 500mm DI K9pipe transmission main from Pachilakunnu tank to Chethadi saw mill jn, Padijaretheruvu to Pulamon jn; Kottarakkara at Vilakudy scour point

Project State Plan - BAWSS to Kundara and adjoining panchayats-Replacement of 500mm DI K9pipe transmission main from Pachilakunnu tank to Chethadi saw mill jn, Padijaretheruvu to Pulamon jn; Kottarakkara at Vilakudy scour point
Project Code KLMGOK02162766P1
Type Package
Main Project State Plan - BAWSS to Kundara and adjoining panchayats-Replacement of 500mm DI K9pipe transmission main from Pachilakunnu tank to Chethadi saw mill jn, Padijaretheruvu to Pulamon jn; Kottarakkara at Vilakudy scour point
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description State Plan - BAWSS to Kundara and adjoining panchayats-Replacement of 500mm DI K9pipe transmission main from Pachilakunnu tank to Chethadi saw mill jn, Padijaretheruvu to Pulamon jn; Kottarakkara at Vilakudy scour point
Status On-going
District Kollam
Executing Office Kundara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 17022016
TS Number 1
Technical specification Supplying and laying of 500mm DI pipe

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/02/2018
Scheduled date of Completion as per agreement 31 May 2017
Expected date of Completion 31/03/2021

Processing Dates

TS Date 01 Apr 2016
Estimate Approval 01 Apr 2016
Tender Closing 20 Aug 2016
Price bid opening 23 Aug 2016

Approval Dates

Workorder Date 16 Jan 2016
NA 23 Nov 2016

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottarakkara PH Dn EE
Date: 09/08/2021

Work in progress | 30% Completed

Clarification for closing the work submitted to Circle office.

Kottarakkara PH Dn EE
Date: 06/08/2021

Work in progress | 30% Completed

Clarification for closing the work submitted to Circle office.