Deposit work - Muttil Grama Panchyath - 2021-22 -RWSS to Muttil Zone 1 to 3 - Pipe line extension to various places in Muttil Grama Panchayath

Project Deposit work - Muttil Grama Panchyath - 2021-22 -RWSS to Muttil Zone 1 to 3 - Pipe line extension to various places in Muttil Grama Panchayath
Project Code WYDDEPO022211789
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - Muttil Grama Panchyath - 2021-22 -RWSS to Muttil Zone 1 to 3 - Pipe line extension to various places in Muttil Grama Panchayath
Status Completed
District Wayanad
Executing Office Kalpetta PH Sn 1
AS Amount (Rs) 2527800
AS Number SC2-3774/2022-23
TS Amount (Rs) 2520000
TS Number TS/2022-2023/2022/8958
Total Bill Submitted (Rs) 1989649
Total Bill Paid (Rs) 1989649
Population Benefitted 1000
Capacity in MLD 10.00
Actual Project Completion Date 06 Jan 2023
Coverage Muttil Grama Panchyath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work - Muttil Grama Panchyath - 2021-22 -RWSS to Muttil Zone 1 to 3 - Pipe line extension to various places in Muttil Grama Panchayath Kalpetta PH Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Apr 2023 Bill submitted to division office Kalpetta PH Sn 1 - AE
24 Apr 2023 bill submitted to subdivision office Kalpetta PH Sn 1 - AE
20 Apr 2023 bill submitted to subdivision office Kalpetta PH Sn 1 - AE
20 Apr 2023 BILL SUBMITTED TO DIVISION OFFICE Kalpetta PH Sn 1 - AE
11 Jan 2023 Work completed. Sulthan Bathery PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/07/2022
Scheduled date of Completion of the Project 06 Jan 2023
Expected date of Completion 06/01/2023

Processing Dates

AS Date 02 Feb 2022
TS Date 07 Jul 2022

Other details

Project Officers View