KIIFB- 2017-18- CWSS to Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths in Chittur and alathur taluks in Palakkad district - Phase I - design, construction, commissioning and maintenance of 26 MLD WTP at POTHUNDY , supplying, laying 600 mm DI k9 pipe for RWPM, road restoration, supply and erection of RW pumpset, transformer
Project |
KIIFB- 2017-18- CWSS to Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths in Chittur and alathur taluks in Palakkad district - Phase I - design, construction, commissioning and maintenance of 26 MLD WTP at POTHUNDY , supplying, laying 600 mm DI k9 pipe for RWPM, road restoration, supply and erection of RW pumpset, transformer |
Project Code |
PKDKIIFB0318634 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
This proposed project is for the implementation of the production components up to water treatment plant of the water supply scheme designed to provide adequate drinking water to the entire population in Elavanchery, Pallassena, Erimayur, Alathur, Kavassery and Puducode grama panchayath of Palakkad district with source as Pothundy Dam.
The existing multiple intake in the well inside the reservoir which is currently used as raw water intake for CWSS to Nenmara Ayilur & Melarcode is proposed to be utilized for this scheme also.
Phase I of the project was sanctioned under KIIFB funding for Rs. 17.58 Crores and includes the components such as construction of 26 MLD Water treatment plant, supplying, laying 600mm DI K9 pipe for Raw water pumping main for 280m including Road restoration, supply & erection of RW Pump set and 630 KVA Transformer, Land acquisition for construction of OHSR in second phase, Power connection charge |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
175800000
|
AS Number |
WRD -025-17/APR-6/2018/KIIFB-PA-01 OF 2018-2019 |
TS Amount (Rs) |
172000000 |
TS Number |
TS/2019-2020/2019/1010 DTD 12.06.19 |
Total Bill Submitted (Rs) |
135031049 |
Total Bill Paid (Rs) |
135031049 |
Population Benefitted |
194774 |
Capacity in MLD |
26.00 |
Actual Project Completion Date |
31 Dec 2021 |
Coverage |
100 lpcd Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB – 2017-18 - Comprehensive drinking water supply project to Elavanchery, Pallassena - PHASE I in Palakkad district |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Sep 2023 |
Work has been completed | 100% Completed | 06/09/2023
All works completed. Agreement executed for supply of energy { HT AND EHT} HT Agreement no 10/2023-2024 dtd 4/09/2023 , {between EE ,KWA,Project division chittur and DCE, Electrical circle ,KSEB,Palakkad |
Chittur Project Dn - AE 1 |
|
12 Aug 2023 |
Work in progress | 98% Completed | 12/08/2023
All works completed. Trial run and commisioning not done for want of KSEB HT Connection, |
Chittur Project Dn - AE 1 |
|
03 Aug 2023 |
Work in progress | 98% Completed | 03/08/2023
All works completed. Trial run and commisioning not done for want of KSEB HT Connection, |
Chittur Project Dn - AE 1 |
|
20 Jul 2023 |
Work in progress | 98% Completed | 20/07/2023
All works completed. Trial run and commisioning not done for want of KSEB HT Connection, |
Chittur Project Dn - AE 1 |
|
13 Jul 2023 |
Work in progress | 98% Completed | 13/07/2023
All works completed. Trial run and commisioning not done for want of KSEB HT Connection, |
Chittur Project Dn - AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/09/2019 |
Scheduled date of Completion of the Project |
24 Mar 2021 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
22 Mar 2018 |
TS Date |
12 Jun 2019 |