Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB- 2017-18- CWSS to Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths in Chittur and alathur taluks in Palakkad district - Phase I - design, construction, commissioning and maintenance of 26 MLD WTP at POTHUNDY , supplying, laying 600 mm DI k9 pipe for RWPM, road restoration, supply and erection of RW pumpset, transformer

Project KIIFB- 2017-18- CWSS to Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths in Chittur and alathur taluks in Palakkad district - Phase I - design, construction, commissioning and maintenance of 26 MLD WTP at POTHUNDY , supplying, laying 600 mm DI k9 pipe for RWPM, road restoration, supply and erection of RW pumpset, transformer
Project Code PKDKIIFB0318634
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This proposed project is for the implementation of the production components up to water treatment plant of the water supply scheme designed to provide adequate drinking water to the entire population in Elavanchery, Pallassena, Erimayur, Alathur, Kavassery and Puducode grama panchayath of Palakkad district with source as Pothundy Dam. The existing multiple intake in the well inside the reservoir which is currently used as raw water intake for CWSS to Nenmara Ayilur & Melarcode is proposed to be utilized for this scheme also. Phase I of the project was sanctioned under KIIFB funding for Rs. 17.58 Crores and includes the components such as construction of 26 MLD Water treatment plant, supplying, laying 600mm DI K9 pipe for Raw water pumping main for 280m including Road restoration, supply & erection of RW Pump set and 630 KVA Transformer, Land acquisition for construction of OHSR in second phase, Power connection charge
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 175800000
AS Number WRD -025-17/APR-6/2018/KIIFB-PA-01 OF 2018-2019
TS Amount (Rs) 172000000
TS Number TS/2019-2020/2019/1010 DTD 12.06.19
Total Bill Submitted (Rs) 135031049
Total Bill Paid (Rs) 135031049
Population Benefitted 194774
Capacity in MLD 26.00
Actual Project Completion Date 31 Dec 2021
Coverage 100 lpcd Pallassena ,Elevanchery ,Alathur,Erimayur, pudukkode and Kavassery panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB – 2017-18 - Comprehensive drinking water supply project to Elavanchery, Pallassena - PHASE I in Palakkad district Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Sep 2023 Work has been completed | 100% Completed | 06/09/2023 All works completed. Agreement executed for supply of energy { HT AND EHT} HT Agreement no 10/2023-2024 dtd 4/09/2023 , {between EE ,KWA,Project division chittur and DCE, Electrical circle ,KSEB,Palakkad Chittur Project Dn - AE 1
12 Aug 2023 Work in progress | 98% Completed | 12/08/2023 All works completed. Trial run and commisioning not done for want of KSEB HT Connection, Chittur Project Dn - AE 1
03 Aug 2023 Work in progress | 98% Completed | 03/08/2023 All works completed. Trial run and commisioning not done for want of KSEB HT Connection, Chittur Project Dn - AE 1
20 Jul 2023 Work in progress | 98% Completed | 20/07/2023 All works completed. Trial run and commisioning not done for want of KSEB HT Connection, Chittur Project Dn - AE 1
13 Jul 2023 Work in progress | 98% Completed | 13/07/2023 All works completed. Trial run and commisioning not done for want of KSEB HT Connection, Chittur Project Dn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/09/2019
Scheduled date of Completion of the Project 24 Mar 2021
Expected date of Completion 31/12/2023

Processing Dates

AS Date 22 Mar 2018
TS Date 12 Jun 2019

Other details

Project Officers View