AMRUT-KollamCorporation-Balance Sewer Network--Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part I- KLM SS-01 andRehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 PartII- KLM SS-02
Project |
AMRUT-KollamCorporation-Balance Sewer Network--Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part I- KLM SS-01 andRehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 PartII- KLM SS-02 |
Project Code |
KLMAMRUT07217919 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Sewerage |
Scheme |
AMRUT |
Description |
AMRUT-KollamCorporation-Balance Sewer Network--Rehabilitation of Existing sewerage system and extension of sewerage system for Zone A1 Part I- KLM SS-01 andRehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 PartII- KLM SS-02 |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
936120000
|
AS Number |
GO(Rt).No.1298/2021/LSGD |
TS Amount (Rs) |
921379526 |
TS Number |
ORDER No. TS/2021-2022/2022/7004 Dated: 23-02-2022 And ORDER No. TS/2021-2022/2022/7010 Dated: 23-02-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
89056 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
31 Mar 2025 |
Coverage |
11 wards in Kollam Corporation ( old municipal area) |
Packages
No. |
Project Name |
Location |
View |
1 |
Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part II KLM SS-02 and for commissioning of Asramom pumping station Balance works - Package III |
Kollam WS Sn 2 |
|
2 |
Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part II KLM SS-02 and for commissioning of H& C I- PALLITHOTTOM and H& C II - Thamarakulam stations Balance works - Package IV |
Kollam WS Sn 2 |
|
3 |
Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part I- KLM SS-01 and for commissioning of Iron Bridge pumping station- Balance works - Package I |
Kollam WS Sn 2 |
|
4 |
Rehabilitation of Existing sewerage system and extension of sewerage system tor Zone A1 Part I- KLM SS-01 and for commissioning of Karumalil and Vaddy pumping stations Balance works - Package II |
Kollam WS Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
(Package 1- Iron Bridge zone , Package 2- Karumalil & Vaddy , Package 3- Asramom Zone ) Estimate for survey work for total station and designing submitted to higher office. * Package 4- Pallithottam & Thamarakkulam-Work in progress. Invert level fixing by total station ongoing.Pipe testing CIPET conducted on 5/3/2024, estimate amount for testing fee submitted by CIPET and submitted to higher office for remitting fee. Detailed drawing submitted to higher office for design approval. |
Kollam WS Sn 2 - AE |
|
08 May 2024 |
(Package 1- Iron Bridge zone , Package 2- Karumalil & Vaddy , Package 3- Asramom Zone ) Estimate for survey work for total station and designing submitted to higher office. * Package 4- Pallithottam & Thamarakkulam-Work in progress. Invert level fixing by total station ongoing.Pipe testing CIPET conducted on 5/3/2024, estimate amount for testing fee submitted by CIPET and submitted to higher office for remitting fee. Detailed drawing submitted to higher office for design approval. |
Kollam WS Sn 2 - AE |
|
04 May 2024 |
(Package 1- Iron Bridge zone , Package 2- Karumalil & Vaddy , Package 3- Asramom Zone ) Estimate for survey work for total station and designing submitted to higher office. * Package 4- Pallithottam & Thamarakkulam-Work in progress. Invert level fixing by total station ongoing.Pipe testing CIPET conducted on 5/3/2024, estimate amount for testing fee submitted by CIPET and submitted to higher office for remitting fee. Detailed drawing submitted to higher office for design approval. |
Kollam WS Sn 2 - AE |
|
30 Apr 2024 |
(Package 1- Iron Bridge zone , Package 2- Karumalil & Vaddy , Package 3- Asramom Zone ) Estimate for survey work for total station and designing submitted to higher office. * Package 4- Pallithottam & Thamarakkulam-Work in progress. Invert level fixing by total station ongoing.Pipe testing CIPET conducted on 5/3/2024, estimate amount for testing fee submitted by CIPET and submitted to higher office for remitting fee. Detailed drawing submitted to higher office for design approval.
|
Kollam WS Sn 2 - AE |
|
27 Apr 2024 |
(Package 1- Iron Bridge zone , Package 2- Karumalil & Vaddy , Package 3- Asramom Zone ) Estimate for survey work for total station and designing submitted to higher office. * Package 4- Pallithottam & Thamarakkulam-Work in progress. Invert level fixing by total station ongoing.Pipe testing CIPET conducted on 5/3/2024, estimate amount for testing fee submitted by CIPET and submitted to higher office for remitting fee. |
Kollam WS Sn 2 - AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
31 Oct 2022 |
Pending |
Pending |
Tender Call Related |
Package I - Iron bridge zone - No offers received for the tender, Recasting estimate submitted in Price.3.0 . Package II -Karumalil and Vaddi zone - Re- tendered & extended, opening date 25/ 10/2022,No offers received, Recast estimate preparation under PRICE . 3 is in progress . Package III - Asramam zone - No offers received on extended date 29/10/2022, as per direction from higher office, Recast estimate preparation in PRICE 3is in progress. Package IV -Thamarakkulam and Pallithottam zone - Recast estimate prepared and submitted in Price 3.0 - AS to be obtained, DER for additional AS submitted |
No comments available. |
Pending |
19 Oct 2022 |
Pending |
Pending |
Tender Call Related |
Package I - Iron bridge zone - No offers received for the tender, Recasting estimate submitted in Price.3.0 . Package II -Karumalil and Vaddi zone - Re- tendered due date 10/10/2022,No offers received, hence extended due date on 22/10/2022 and opening date 25/10/2022 . Package III - Asramam zone - No offers received on 16.10.2022 ,hence extended due date 27/10/2022 and opening date 29/10/2022. Package IV -Thamarakkulam and Pallithottam zone - Recast estimate prepared and submitted in Price 3.0 - AS to be obtained, DER for additional AS submitted |
No comments available. |
Pending |
10 Oct 2022 |
Pending |
Pending |
Tender Call Related |
Repeated tender calls no offers received |
No comments available. |
Pending |
17 Sep 2022 |
Pending |
Pending |
Tender Call Related |
Package I - Iron bridge zone - No offers received for the tender, Recasting estimate submitted in Price.3.0 . Package II -Karumalil and Vaddi zone - Re- tendered due date 31/8/2022 ,No offers received.Hence extended due date on 22.09.2022 . Package III - Asramam zone - No offers received,hence re -tendered due date on 03.10.2022. Package IV -Thamarakkulam and Pallithottam zone - Recast estimate prepared and submitted in Price 3.0 - AS to be obtained, DER for additional AS submitted |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
25/02/2022 |
Scheduled date of Completion of the Project |
30 Jun 2024 |
Expected date of Completion |
30/06/2024 |
Processing Dates
AS Date |
09 Jul 2021 |
TS Date |
23 Feb 2022 |