JJM - NABL- Accreditation - modernizing - 86 mld Water Treatment plant at Aruvikkara
Project |
JJM - NABL- Accreditation - modernizing - 86 mld Water Treatment plant at Aruvikkara |
Project Code |
TVMJJM09218451 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - NABL- Accreditation - modernizing - 86 mld Water Treatment plant at Aruvikkara |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum QC Sn |
AS Amount (Rs) |
5200000
|
AS Number |
GO(Rt) No. 489/2021/WRD |
TS Amount (Rs) |
1400000 |
TS Number |
TS/2021-2022/2021/23728 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - NABL- Accreditation - modernizing - 86 mld Water Treatment plant at Aruvikkara |
Quality division TVM |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Feb 2022 |
Aluminium Partition going on . About 75 % work completed. |
Thiruvananthapuram QC AE 1 |
|
16 Feb 2022 |
Flooring and granite slab work going on. About 50 % completed. |
Thiruvananthapuram QC AE 1 |
|
10 Feb 2022 |
Electrical wiring going on in the Microbiology lab. 45 % work completed. |
Thiruvananthapuram QC AE 1 |
|
02 Feb 2022 |
False ceiling work going on. About 40 % work completed. |
Thiruvananthapuram QC AE 1 |
|
25 Jan 2022 |
Electrification work going on,about 35% work completed. |
Thiruvananthapuram QC AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/11/2021 |
Scheduled date of Completion of the Project |
31 Jan 2022 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
22 Oct 2021 |