Project | DEPOSIT-CSME-Providing water supply service connection to Galaxy Bridgewood at Bund road jn-Kochappilly road,Chilavannoor in Div No 28(old) of Kochi Corporation |
---|---|
Project Code | EKMDEPO012314957P1 |
Type | Package |
Main Project | DEPOSIT-CSME-Providing water supply service connection to Galaxy Bridgewood at Bund road jn-Kochappilly road,Chilavannoor in Div No 28(old) of Kochi Corporation |
Funding Agency | DEPO |
Category | CSME |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | DEPOSIT-CSME-Providing water supply service connection to Galaxy Bridgewood at Bund road jn-Kochappilly road,Chilavannoor in Div No 28(old) of Kochi Corporation |
Status | On-going |
District | Ernakulam |
Executing Office | Vytilla Section 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 870000 |
TS Number | TS/11573/2022 |
Technical specification | DEPOSIT-CSME-Providing water supply service connection to Galaxy Bridgewood at Bund road jn-Kochappilly road,Chilavannoor in Div No 28(old) of Kochi Corporation |
Contractor | A.B Gopalakrishnan (Mob: 9995093125) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 16 Jan 2024 |
Expected date of Completion | 16/01/2024 |
TS Date | 04 Feb 2023 |
---|---|
Estimate Approval | 06 Jan 2023 |
NIT Approval | 14 Feb 2023 |
Tender Closing | 24 Feb 2023 |
Technichal Pre-Qualification | 24 Feb 2023 |
Price bid opening | 25 Feb 2023 |
Workorder Date | 04 Oct 2023 |
---|---|
NA | 17 Oct 2023 |
Vytilla Section AE - 2 |
Date: 29/01/2024 |
Work has been completed | 100% Completed
final bill submitted on 22.01.24.
Vytilla Section AE - 2 |
Date: 12/01/2024 |
Work has been completed | 100% Completed
Work completed.