Jal Jeevan Mission in Elampalloor panchayath ;-RWSS to Punukkannoorchira- Supply erection and commissioning of wall mounted gravity feed chlorinator of capacity 2kg/hr with P.H Meter and Turbidity meter for,3 MLD WTP at Punukkannoorchira Plant

Project Jal Jeevan Mission in Elampalloor panchayath ;-RWSS to Punukkannoorchira- Supply erection and commissioning of wall mounted gravity feed chlorinator of capacity 2kg/hr with P.H Meter and Turbidity meter for,3 MLD WTP at Punukkannoorchira Plant
Project Code KLMJJM082010409
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission in Elampalloor panchayath ;-RWSS to Punukkannoorchira- Supply erection and commissioning of wall mounted gravity feed chlorinator of capacity 2kg/hr with P.H Meter and Turbidity meter for,3 MLD WTP at Punukkannoorchira Plant
Status Completed
District Kollam
Executing Office Kundara PH Sn
AS Amount (Rs) 20370000
AS Number GO. (Rt) no.541/2020/WRD
TS Amount (Rs) 418527
TS Number TS/2021-2022/2021/36067
Total Bill Submitted (Rs) 417000
Total Bill Paid (Rs) 417000
Population Benefitted 22000
Capacity in MLD 3.00
Actual Project Completion Date 21 Jun 2022
Coverage Elampaloor pt
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission in Elampalloor panchayath ;-RWSS to Punukkannoorchira- Supply erection and commissioning of wall mounted gravity feed chlorinator of capacity 2kg/hr with P.H Meter and Turbidity meter for,3 MLD WTP at Punukkannoorchira Plant Kundara PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2022 work completed Kottarakkara PH Dn EE
16 May 2022 work completed Kottarakkara PH Dn EE
13 May 2022 work on progress Kottarakkara PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/05/2022
Scheduled date of Completion of the Project 21 Jun 2022
Expected date of Completion 21/06/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 05 Jan 2022

Other details

Project Officers View