Project | Block deposit work - RWSS to Arakuzha- Extension of pipeline to Nedumpara SC Colony in ward No.VII of Arakuzha Grama Panchayath. |
---|---|
Project Code | EKMDEPO09197268P1 |
Type | Package |
Main Project | Block deposit work - RWSS to Arakuzha- Extension of pipeline to Nedumpara SC Colony in ward No.VII of Arakuzha Grama Panchayath. |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Block deposit work - RWSS to Arakuzha- Extension of pipeline to Nedumpara SC Colony in ward No.VII of Arakuzha Grama Panchayath. |
Status | Completed |
District | Ernakulam |
Executing Office | Muvattupuzha PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 300000 |
TS Number | 10227/2019-2020 |
Technical specification | The work includes 1. laying 50 mm GI(M) pipes for a length of 450 m, 2. Shifting 12 existing house connections to new line, 3. Providing 2 air valves and 4. Recasting demolished RCC etc., |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/06/2020 |
---|---|
Scheduled date of Completion as per agreement | 04 Jul 2020 |
Expected date of Completion | 04/07/2020 |
TS Date | 07 Mar 2020 |
---|---|
Estimate Approval | 07 Mar 2020 |
NIT Approval | 07 Mar 2020 |
Tender Closing | 25 Mar 2020 |
Technichal Pre-Qualification | 07 Mar 2020 |
Price bid opening | 25 Mar 2020 |
Workorder Date | 29 May 2020 |
---|---|
NA | 05 Jun 2020 |
Muvattupuzha PH Section - AE |
Date: 13/06/2022 |
Work has been completed | 100% Completed
100% Completed.
Muvattupuzha PH Section - AE |
Date: 09/06/2022 |
Work has been completed | 100% Completed
100% Completed.