- Home
- Deposit work - ARWSS to Kumily- Extensio...
Deposit work - ARWSS to Kumily- Extension of pipe line Paliyakudy Tribal Colony in ward 13 of Kumily Grama panchayat -
| Project |
Deposit work - ARWSS to Kumily- Extension of pipe line Paliyakudy Tribal Colony in ward 13 of Kumily Grama panchayat - |
| Project Code |
IDKDEPO042210062 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposit work - ARWSS to Kumily- Extension of pipe line Paliyakudy Tribal Colony in ward 13 of Kumily Grama panchayat - |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Kattappana Project Dn |
| AS Amount (Rs) |
398000
|
| AS Number |
111/2021/DPC/DPO/IDK |
| TS Amount (Rs) |
397693 |
| TS Number |
TS/2021-2022/2020/15051 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Paliyakudy Tribal Colony in ward 13 of Kumily Grama panchayat |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit work -ARWSS To Kumily Extension of pipe line Paliyakudy Tribal Colony in Ward 13 Of Kumily Grama Panchyath |
Project Division Kattapana |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
11/04/2022 |
| Scheduled date of Completion of the Project |
09 Jun 2022 |
| Expected date of Completion |
31/05/2022 |
Processing Dates
| AS Date |
10 Sep 2021 |
| TS Date |
10 Sep 2022 |