Deposit work – cwss to koyilandy and adj; Panchayats – pipe line extension to valiyaparambil Bhagam in ward No. 10 at changaroth Panchayat
Project |
Deposit work – cwss to koyilandy and adj; Panchayats – pipe line extension to valiyaparambil Bhagam in ward No. 10 at changaroth Panchayat |
Project Code |
CLTDEPO07207247 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work – cwss to koyilandy and adj; Panchayats – pipe line extension to valiyaparambil Bhagam in ward No. 10 at changaroth Panchayat |
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Vadakara PH Dn |
AS Amount (Rs) |
230000
|
AS Number |
A2-2882/20 |
TS Amount (Rs) |
230000 |
TS Number |
4167/20-21 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work – cwss to koyilandy and adj; Panchayats – pipe line extension to valiyaparambil Bhagam in ward No. 10 at changaroth Panchayat |
Perambra PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Jan 2022 |
5% to be completed |
Vadakara PH Dn EE |
|
20 Jan 2022 |
95% work completed |
Vadakara PH Dn EE |
|
13 Jan 2022 |
WORK IN PROGRESS |
Vadakara PH Dn EE |
|
21 Dec 2021 |
Work in progress |
Vadakara PH Dn EE |
|
29 Nov 2021 |
Work in progress |
Vadakara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/11/2020 |
Scheduled date of Completion of the Project |
01 Feb 2021 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
09 Jul 2020 |
TS Date |
21 Jul 2020 |