Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Sep 2023 | Final bill submitted on 14/09/2023. | Kannur WS Sn AE 2 | |
13 Sep 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
10 Sep 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
07 Sep 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
03 Sep 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
30 Aug 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
27 Aug 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
24 Aug 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
21 Aug 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 | |
18 Aug 2023 | Work Completed. 1st and final bill under preparation. | Kannur WS Sn AE 2 |