Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2023 | pipe line work on going | Malapuram Proj Dn AE 4 | |
24 May 2023 | 400 mm DI ,300 mm DI, 250 mm DI and 200 mm DI pipes supplied and well piling work | Malapuram Proj Dn AE 4 | |
11 May 2023 | 400 mm DI ,300 mm DI, 250 mm DI and 200 mm DI pipes supplied | Malapuram Proj Dn AE 4 | |
05 May 2023 | 400 mm DI ,300 mm DI, 250 mm DI and 200 mm DI pipes supplied | Malapuram Proj Dn AE 4 |