| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Oct 2024 | 6 KM pipe laid. 836 Nos FHTC given | Kannur PH Sn 3 AE | |
| 24 Oct 2024 | 6 KM pipe laid. 836 Nos FHTC given | Kannur PH Sn 3 AE | |
| 22 Oct 2024 | 6 KM pipe laid. 836 Nos FHTC given | Kannur PH Sn 3 AE | |
| 18 Oct 2024 | 6 KM pipe laid. 290 Nos FHTC given | Kannur PH Sn 3 AE | |
| 07 Oct 2024 | 6 KM pipe laid. 270 Nos FHTC given | Kannur PH Sn 3 AE | |
| 20 Sep 2024 | 6 KM pipe laid. 230 Nos FHTC given | Kannur PH Sn 3 AE | |
| 08 Aug 2024 | 6 KM pipe laid. 230 Nos FHTC given | Kannur PH Sn 3 AE | |
| 23 Jul 2024 | 6 KM pipe laid. 230 Nos FHTC given | Kannur PH Sn 3 AE | |
| 03 Jul 2024 | 6 KM pipe laid. 230 Nos FHTC given | Kannur PH Sn 3 AE | |
| 01 Jun 2024 | 6 KM pipe laid. 220 Nos FHTC given | Kannur PH Sn 3 AE |