| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Jun 2021 | out of 900nos. 5th part bill submitted for 100 Connections as on 25.05.2021 | Nenmara Sn AE | |
| 20 Jun 2021 | out of 900nos. 4th part bill submitted for 150 Connections as on 29.04.2021 | Nenmara Sn AE | |
| 20 Apr 2021 | out of 900nos. 3rd part bill submitted for 200 Connections as on 20.04.2021 | Nenmara Sn AE | |
| 25 Mar 2021 | out of 900nos. Second part bill submitted for 100 Connections as on 19.03.2021 | Nenmara Sn AE | |
| 25 Mar 2021 | out of 895nos. First part bill submitted for 100 Connections as on 19.03.2020 | Nenmara Sn AE | |
| 25 Mar 2021 | out of 900nos. First part bill submitted for 80 Connections as on 27.02.2021 | Nenmara Sn AE | |
| 25 Mar 2021 | FHTC 100nos given as on 19.03.2021 out of 900nos. Second part bill submitted | Nenmara Sn AE | |
| 25 Mar 2021 | FHTC 80nos given as on 27.02.2021 out of 900nos. First part bill submitted | Nenmara Sn AE | |
| 07 Feb 2021 | Agreement executed . Work to be started | Chittur PH Sub Dn AEE | |
| 28 Nov 2020 | Work to be retendered. | Palakkad PH Dn EE |