| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Jan 2026 | Koodali - Thandappuram RHS side BM work completed | Mattannur WS Sn | |
| 06 Jan 2026 | Koodali - Thandappuram RHS side BM work completed | Mattannur WS Sn | |
| 29 Dec 2025 | Koodali - Thandappuram RHS side BM work completed | Mattannur WS Sn | |
| 20 Dec 2025 | Koodali - Thandappuram RHS side BM work completed | Mattannur WS Sn | |
| 25 Nov 2025 | 40% work completed | Mattannur WS Sn | |
| 14 Nov 2025 | 40% work completed. | Mattannur WS Sn | |
| 05 Nov 2025 | work not started | Mattannur WS Sn | |
| 15 Oct 2025 | work not started | Mattannur WS Sn | |
| 03 Oct 2025 | work not started | Mattannur WS Sn | |
| 22 Sep 2025 | work not started | Mattannur WS Sn |