Status Date Overall Project Status Project Officer Contact
15 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
13 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
10 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
08 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
04 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
01 Dec 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
29 Nov 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
26 Nov 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
24 Nov 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE
22 Nov 2021 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting Kottayam PHMC AE