Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Oct 2024 | Pipe laying distribution 100% completed.Pumping and gravity main 99% completed.Reservoirs of 6.0LL GLSR & 1.0LL GLSR completed.Power connection is awaiting | Mattannur Project Sn 2 AE | |
06 Feb 2024 | PIPE LAYING 90% COMPLETED.TOTAL HTC GEO TAAGED 3313nos | Mattannur Project Sn 2 AE | |
30 Jul 2023 | Pipe laying and HTC work is in progress. | Mattannur Project Sn 2 AE | |
26 Jun 2023 | Pipe laying ,house connection 80% completed and HTC work on progress.1.00LL Capacity GLSR at kanhiradmala completed.6.00LL Capacity GLSR at Kanhirad is in progress | Mattannur Project Sn 2 AE |