Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Mar 2023 | Work completed. | Kozhikode Project Dn AE5 | |
28 Mar 2023 | 90mm - 17000 m laid, 635 FHTCs and 835 HTCs provided, Work in progress. | Kozhikode Project Dn AE5 | |
20 Mar 2023 | 90mm - 17000 m laid, 635 FHTCs and 803 HTCs provided, Work in progress. | Kozhikode Project Dn AE5 | |
10 Mar 2023 | 90mm - 17000 m laid, 635 FHTCs and 760 HTCs provided, Work in progress. | Kozhikode Project Dn EE | |
06 Mar 2023 | 90mm - 17000 m laid, 635 FHTCs and 720 HTCs provided, Work in progress. | Kozhikode Project Dn AE5 | |
14 Feb 2023 | 90mm - 16400 m laid, 635 FHTCs and 590 HTCs provided, Work in progress. | Kozhikode Project Dn EE | |
10 Feb 2023 | 90mm - 16400 m laid, 635 FHTCs and 565 HTCs provided, Work in progress. | Kozhikode Project AEE 1 | |
31 Jan 2023 | 90mm - 14000 m laid, 635 FHTCs and 492 HTCs provided, Work in progress. | Kozhikode Project Dn AE5 | |
24 Jan 2023 | 90mm - 13250 m laid, 635 FHTCs and 429 HTCs provided, Work in progress. | Kozhikode Project Dn AE5 | |
12 Jan 2023 | 90mm - 13250 m laid, 635 FHTCs and 388 HTCs provided, Work in progress. | Kozhikode Project Dn EE |