| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Nov 2021 | 200 mm DI PIPE Laying 93%Work completed, 911Nos FHTCs provided. | Chalakudy AE 2 | |
| 03 Nov 2021 | CC 1 st and part bill of JJM Pariyaram Grama Panchayath (Appendix B)-Providing FHCTCs to Rural house holds by ongoing works submitted to Sub division | Chalakudy AE 2 | |
| 01 Nov 2021 | 200 mm DI PIPE Laying 93%Work completed, 911Nos FHTCs provided. | Chalakudy AE 2 | |
| 30 Oct 2021 | 200 mm DI PIPE Laying 93%Work completed, 911Nos FHTCs provided. | Chalakudy AE 2 | |
| 29 Oct 2021 | 200 mm DI PIPE Laying 93%Work completed, 854Nos FHTCs provided. | Chalakudy AE 2 | |
| 28 Oct 2021 | 200 mm DI PIPE Laying 92%Work completed, 854Nos FHTCs provided. | Chalakudy AE 2 | |
| 26 Oct 2021 | 200 mm DI PIPE Laying 92%Work completed, 810Nos FHTCs provided. | Chalakudy AE 2 | |
| 25 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 782Nos FHTCs provided. | Chalakudy AE 2 | |
| 22 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 21 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 |