| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Apr 2026 | Intake well -Side wall 2nd lift completed | Payyannur UIDSSMT AE 3 | |
| 07 Apr 2026 | Intake well -Side wall 1st lift completed | Payyannur UIDSSMT AE 3 | |
| 30 Mar 2026 | Intake well -Side wall 1st lift completed | Payyannur UIDSSMT AE 3 | |
| 23 Mar 2026 | Intake well -Base slab and kerb completed. | Payyannur UIDSSMT AE 3 | |
| 11 Mar 2026 | Intake well -PCC completed | Payyannur UIDSSMT AE 3 | |
| 03 Mar 2026 | Intake well -Earth work excavation is progressing | Payyannur UIDSSMT AE 3 | |
| 25 Feb 2026 | Intake well -Earth work excavation is progressing | Payyannur UIDSSMT AE 3 | |
| 17 Feb 2026 | intake well -Earth work excavation is progressing | Payyannur UIDSSMT AE 3 | |
| 11 Feb 2026 | intake well -Earth work excavation is progressing | Payyannur UIDSSMT AE 3 | |
| 03 Feb 2026 | intake well -excavation of earth work is progressing | Payyannur UIDSSMT AE 3 |