| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Sep 2021 | Work Completed Successfully. | Kochi WS Dn EE | |
| 04 Sep 2021 | 687 FHTCs given | Kochi WS Dn EE | |
| 21 Aug 2021 | 655 FHTC given | Kochi WS Dn EE | |
| 30 Jul 2021 | 645 FHTC given | Kochi WS Dn EE | |
| 20 Jul 2021 | 640 Nos FTHC given | Kochi WS Dn EE | |
| 15 Jul 2021 | 628 Nos FHTC given | Kochi WS Dn EE | |
| 15 Jul 2021 | 623 Nos FHTC given | Kochi WS Dn EE | |
| 10 Jul 2021 | 628 Nos FHTC given | Kochi WS Dn EE | |
| 09 Jul 2021 | 593 FHTC's given, CC 4th and part bill submitted | Kochi WS Dn EE | |
| 01 Jul 2021 | 564 FHTC's given, CC 4 th Bill Under Verification | Kochi WS Dn EE |