Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Oct 2023 | work started | Cherthala PH Section - AE | |
12 Jul 2023 | Work shall be completed after the construction of bridge by PWD | Cherthala PH SUb Dn | |
19 Jun 2023 | Work Started | Alappuzha PH Dn EE | |
09 Jun 2023 | Agreement executed | Alappuzha PH Dn EE | |
09 Jun 2023 | Agreement executed | Alappuzha PH Dn EE |