Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Feb 2022 Work has been completed - 514 m of 50 mm PVC pipes were laid Kozhinjampara PH Sn AE
09 Feb 2022 360 m of 50 mm PVC pipe was laid Kozhinjampara PH Sn AE
01 Feb 2022 120 m of 63 mm PVC pipe was laid Kozhinjampara PH Sn AE
09 Nov 2021 updated Palakkad PH Dn EE