| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Feb 2022 | Work has been completed - 514 m of 50 mm PVC pipes were laid | Kozhinjampara PH Sn AE | |
| 09 Feb 2022 | 360 m of 50 mm PVC pipe was laid | Kozhinjampara PH Sn AE | |
| 01 Feb 2022 | 120 m of 63 mm PVC pipe was laid | Kozhinjampara PH Sn AE | |
| 09 Nov 2021 | updated | Palakkad PH Dn EE |