Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Apr 2024 | Concrete work for Bottom slab of Box culvert is going on | Plamoodu Sewerage Project Sn AE | |
17 Apr 2024 | Work for dismantling the existing box culvert is in progress. | Plamoodu Sewerage Project Sn AE | |
10 Apr 2024 | Work for dismantling the existing box culvert is in progress. | Plamoodu Sewerage Project Sn AE | |
22 Mar 2024 | Work for diverting of flow of thodu is in progress | Plamoodu Sewerage Project Sn AE | |
15 Mar 2024 | Work for diverting of flow of thodu is in progress | Plamoodu Sewerage Project Sn AE | |
14 Mar 2024 | Work for dismantling the existing box culvert is in progress. | Plamoodu Sewerage Project Sn AE | |
07 Mar 2024 | Box culvert work is to be started by the contractor and today there was no work at site. Contractor was given a reminder letter directing to complete the work before monsoon. | Plamoodu Sewerage Project Sn AE | |
26 Feb 2024 | Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. | Plamoodu Sewerage Project Sn AE | |
12 Feb 2024 | Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. | Plamoodu Sewerage Project Sn AE | |
06 Feb 2024 | Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. | Plamoodu Sewerage Project Sn AE |