Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Apr 2024 Concrete work for Bottom slab of Box culvert is going on Plamoodu Sewerage Project Sn AE
17 Apr 2024 Work for dismantling the existing box culvert is in progress. Plamoodu Sewerage Project Sn AE
10 Apr 2024 Work for dismantling the existing box culvert is in progress. Plamoodu Sewerage Project Sn AE
22 Mar 2024 Work for diverting of flow of thodu is in progress Plamoodu Sewerage Project Sn AE
15 Mar 2024 Work for diverting of flow of thodu is in progress Plamoodu Sewerage Project Sn AE
14 Mar 2024 Work for dismantling the existing box culvert is in progress. Plamoodu Sewerage Project Sn AE
07 Mar 2024 Box culvert work is to be started by the contractor and today there was no work at site. Contractor was given a reminder letter directing to complete the work before monsoon. Plamoodu Sewerage Project Sn AE
26 Feb 2024 Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. Plamoodu Sewerage Project Sn AE
12 Feb 2024 Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. Plamoodu Sewerage Project Sn AE
06 Feb 2024 Out of 167.50m of 600 mm RCC NP3 pipe, 145m laid and 11 MH completed. Sanction was accorded by Irrigation Department to lay DI pipe across the box culvert. Hence contractor was requested to complete the work immediately. Plamoodu Sewerage Project Sn AE