Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Jun 2021 | 100% completed | Kochi QC Dn EE | |
29 Apr 2021 | 90% completed. Chemical lab 90% completed. | Kochi QC Dn EE | |
16 Apr 2021 | 75% completed. Chemical lab 90% completed. | Kochi QC Dn EE | |
12 Mar 2021 | chemical Lab 60% progressed. Electrical work, Partition work, Painting being done. | Kochi QC Dn EE | |
04 Mar 2021 | 45% completed | Kochi QC Dn EE | |
25 Feb 2021 | 40% completed | Kochi QC Dn EE | |
16 Feb 2021 | 30% progressed | Kochi QC Dn EE | |
10 Feb 2021 | work in progress | Kochi QC Dn EE | |
27 Jan 2021 | project office and PPD office Plakkad shifted and space handed over on 28.12.2020. Work in progress. 20% completed | Kochi QC Dn EE | |
23 Nov 2020 | Agreement can be executed after Election | Kochi QC Dn EE |