Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jun 2021 28% of package 1 and 34% of package2 completed Revised estimate got approved to facilitate the changes in the raw water pipe line alignment and location of well cum pump house in package 1 Malappuram Project Dn AE3
01 Jun 2021 28% of Package 1 and 34 % of Package 2 Completed. Malappuram Project Dn AE3
26 May 2021 28% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
05 May 2021 26% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
26 Apr 2021 26% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
19 Apr 2021 26% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
13 Apr 2021 25% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
12 Apr 2021 25% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
09 Apr 2021 24% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3
08 Apr 2021 24% of Package 1 and 33% of Package 2 Completed. Malappuram Project Dn AE3