Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Jun 2021 | 28% of package 1 and 34% of package2 completed Revised estimate got approved to facilitate the changes in the raw water pipe line alignment and location of well cum pump house in package 1 | Malappuram Project Dn AE3 | |
01 Jun 2021 | 28% of Package 1 and 34 % of Package 2 Completed. | Malappuram Project Dn AE3 | |
26 May 2021 | 28% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
05 May 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
26 Apr 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
19 Apr 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
13 Apr 2021 | 25% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
12 Apr 2021 | 25% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
09 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
08 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 |