Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Feb 2022 In package 1, 61%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4400 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 71%- 29382 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29382 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Package 3, Under tendering process. Malappuram Project Dn AE3
12 Feb 2022 In package 1, 61 %- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4237.5 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 71 % - 29281 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29281 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3
05 Feb 2022 In package 1,60 % Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 691 m (600mm DI) laying done .Clear water pumping main work under progress. 1109 m (250 mm DI) piping done. Well excavation work in progress. In package 2, 70 %- 29206 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29206 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Malappuram Project Dn AE3
29 Jan 2022 In package 1 60 %, Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 691 m (600mm DI) laying done .Clear water pumping main work under progress. 1109 m (250 mm DI) piping done. Well excavation work in progress. In package 2, 68 %- 27696 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 27696 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Package 3, Under tendering process. Malappuram Project Dn AE3
25 Jan 2022 In package 1 60 %, Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 691 m (600mm DI) laying done .Clear water pumping main work under progress. 1109 m (250 mm DI) piping done. Well excavation work in progress. In package 2, , 68 %- 27676 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 27676 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Package 3, Under tendering process. Malappuram Project Dn AE3
18 Jan 2022 In Package 1, 59 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed. Variation, due to the change in well cum pump house location ,has been got approved by KIIFB now.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 691 m (600mm DI) laying done .Clear water pumping main work under progress. 1109 m (250 mm DI) piping done. In package 2, 68 %- 27661 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 27661 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Malappuram Project Dn AE3
11 Jan 2022 In package 1, 58 % WTP finishing work progress, Well site clearance work and Raw water pumping main started. In package 2, 67 %. 27576 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 27576 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. Malappuram Project Dn AE3
11 Jan 2022 58% of Package 1 and 67% Package 2 completed Malappuram Project Dn AE3
10 Jan 2022 58% of Package 1 and 64% Package 2 completed Malappuram Project Dn AE3
03 Jan 2022 58% of Package 1 and 64% Package 2 completed Malappuram Project Dn AE3