| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Aug 2021 | Work Completed Successfully. | Kochi WS Dn EE | |
| 16 Aug 2021 | 1000 FHTCS given | Kochi WS Dn EE | |
| 30 Jul 2021 | 840 Nos FHTC given | Kochi WS Dn EE | |
| 22 Jul 2021 | 800 FHTC's Given | Kochi WS Dn EE | |
| 15 Jul 2021 | 737 Nos FHTC's given | Kochi WS Dn EE | |
| 09 Jul 2021 | 686 FHTC's given | Kochi WS Dn EE | |
| 01 Jul 2021 | 628 FHTC Given,work slow due to lockdown | Kochi WS Dn EE | |
| 25 Jun 2021 | 628 FHTC Given,work slow due to lockdown | Kochi WS Dn EE | |
| 17 Jun 2021 | 628 FHTC Given,work slow due to lockdown | Kochi WS Dn EE | |
| 09 Jun 2021 | 628 FHTC Given,work slow due to lockdown | Kochi WS Dn EE |