Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Feb 2022 | work completed | Kayamkulam AE | |
02 Feb 2022 | work completed | Kayamkulam AE | |
10 Jan 2022 | Tank Demolishing work progressing ( 2 NOS) in Deikulangara panchayat | Kayamkulam AE | |
05 Jan 2022 | Tank Demolishing work progressing ( 2 NOS) in Deikulangara panchayat | Kayamkulam AE | |
27 Dec 2021 | Tank Demolishing work progressing ( 2 NOS) in Deikulangara panchayat | Kayamkulam AE | |
20 Dec 2021 | Tank Demolishing work progressing ( 2 NOS) in Deikulangara panchayat | Kayamkulam AE | |
13 Dec 2021 | Tank Demolition work progressing ( 2 NOS) in Deikulangara panchayat | Kayamkulam AE | |
29 Nov 2021 | SELECTION NOTICE ISSUED FOR MANNEL KADAVU &DEMOLISHING WORK STARTED FOR DEVIKULANGARA PH ( IN DEVIKULANGARA PANCHAYATH), PATTOLI MARKET - DEMOLISHING WORK COMPLETED & MANGALAM TANK - BILL SUBMITTED TO SUB DN | Kayamkulam AE | |
22 Nov 2021 | SELECTION NOTICE ISSUED FOR DEVIKULANGARA PH &MANNEL KADAVU( IN DEVIKULANGARA PANCHAYATH), PATTOLI MARKET - DEMOLISHING WORK COMPLETED & MANGALAM TANK - BILL SUBMITTED TO SUB DN | Kayamkulam AE | |
15 Nov 2021 | SELECTION NOTICE ISSUED FOR DEVIKULANGARA PH &MANNEL KADAVU( IN DEVIKULANGARA PANCHAYATH), PATTOLI MARKET - DEMOLISHING WORK COMPLETED & MANGALAM TANK - BILL SUBMITTED TO SUB DN | Kayamkulam AE |