| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Jun 2025 | Work awarded to MUHAMMED RIYAS K C on 11-6-2025. | Kattappana AEE 1 | |
| 12 Jun 2025 | LoA issued on 11-06-2025. | Kattappana AEE 1 | |
| 09 Jun 2025 | For LoA Preperation | Kattappana AEE 1 | |
| 06 Jun 2025 | For Tender Approval | Kattappana AEE 1 | |
| 03 Jun 2025 | For Tender Review | Kattappana AEE 1 | |
| 31 May 2025 | For Tender Scrutiny | Kattappana AEE 1 | |
| 28 May 2025 | For Tender Scrutiny | Kattappana AEE 1 | |
| 25 May 2025 | For Tender Approval | Kattappana AEE 1 | |
| 22 May 2025 | For Tender Approval | Kattappana AEE 1 | |
| 22 May 2025 | PQ sanctioned, and three bidders have been disqualified. The provisional PQ is currently under process. | Kattappana AEE 1 |