| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Oct 2024 | No response, work to be retendered. | Perlasserry Sn 1 | |
| 14 Oct 2024 | No response, work to be retendered. | Kannur PH Dn EE | |
| 04 Oct 2024 | Work retendered. | Kannur PH Dn EE | |
| 27 Sep 2024 | Work retendered. | Kannur PH Dn EE | |
| 24 Sep 2024 | No response, work to be retendered. | Kannur PH Dn EE | |
| 19 Sep 2024 | No response, work to be retendered. | Kannur PH Dn EE | |
| 05 Sep 2024 | Estimate submitted to SE. | Kannur PH Dn EE | |
| 29 Aug 2024 | Estimate submitted to SE. | Kannur PH Dn EE | |
| 23 Aug 2024 | Estimate submitted to SE. | Kannur PH Dn EE | |
| 14 Aug 2024 | AS Accorded on 23/07/2024, Work to be tendered. | Kannur PH Dn EE |