| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Mar 2021 | third stage column concrete in progressing | Kollam Project HD | |
| 27 Mar 2021 | third stage colum concreting progressing | Kollam Project HD | |
| 27 Mar 2021 | third stage colum concreting progressing | Kollam Project HD | |
| 24 Mar 2021 | SECOND STAGE INTERMEDIATE SLAB CONCRETED . | Kollam Project HD | |
| 02 Mar 2021 | 455m of transmission main laid | Kollam Project HD | |
| 20 Feb 2021 | Transmission line laying and OHSR stage 2 works in progress | Kollam Project HD | |
| 14 Feb 2021 | re started the laying of transmission main | Kollam Project HD | |
| 12 Feb 2021 | Second stage shuttering in process | Kollam Project HD | |
| 11 Feb 2021 | Satge one completed.Second stage shuttering in process. | Kollam Project HD | |
| 09 Feb 2021 | stair case concreting in process | Kollam Project HD |