| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Jun 2025 | Work Completed. | Thaliparamba WS Sub Dn | |
| 14 Feb 2024 | Balance work started .20 FHTCs out of 60 FHTCs completed | Thaliparamba WS Dn EE | |
| 28 Feb 2022 | 5313 FHTCs completed under JJM | Kalliassery W S Section - AE | |
| 04 Feb 2022 | 4704 FHTC s out of 5549 FHTC s completed | Kalliassery W S Section - AE | |
| 27 Jul 2021 | 3090/5549 | Thaliparamba WS Dn EE | |
| 19 Jul 2021 | 3090/5549 | Thaliparamba WS Dn EE | |
| 29 Jun 2021 | Work progress is effected due to water logging in the area. CC 6th and part bill submitted. | Thaliparamba WS Dn EE | |
| 12 Jun 2021 | 3080 FHTCs out of 5549 FHTCs completed (55%). | Thaliparamba WS Dn EE | |
| 01 Jun 2021 | 2935/5549 FHTCs completed | Thaliparamba WS Dn EE | |
| 16 Apr 2021 | 1959/5549 FHTCs compleyed | Thaliparamba WS Dn EE |