Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Mar 2024 | Bill submitted for an amt. of 2979827.00 | Vytilla HW AE | |
19 Mar 2024 | work in progress | Vytilla HW AE | |
13 Mar 2024 | work in progress | Vytilla HW AE | |
11 Mar 2024 | work in progress | Vytilla HW AE | |
07 Mar 2024 | work in progress | Vytilla HW AE | |
07 Mar 2024 | work in progress | Vytilla HW AE | |
05 Mar 2024 | work in progress | Vytilla HW AE | |
04 Mar 2024 | Work in progress | Vytilla HW AE | |
29 Feb 2024 | Work in progress | Vytilla HW AE | |
24 Feb 2024 | plastering under progress | Vytilla HW AE |