Status Date Overall Project Status Project Officer Contact
18 Dec 2024 Trial running to be completed. Koothuparambu PH Sn AE
10 Dec 2024 Trial running to be completed. Koothuparambu PH Sn AE
03 Dec 2024 Trial running to be completed. Koothuparambu PH Sn AE
26 Nov 2024 Trial running to be completed. Koothuparambu PH Sn AE
19 Nov 2024 Trial running to be completed. Koothuparambu PH Sn AE
13 Nov 2024 Trial running to be completed. Koothuparambu PH Sn AE
07 Nov 2024 Work in progress. Koothuparambu PH Sn AE
02 Nov 2024 Work in progress. Koothuparambu PH Sn AE
26 Oct 2024 Site handed over, Work started. Koothuparambu PH Sn AE
21 Oct 2024 Agreement Executed Kannur PH Dn EE