Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Oct 2024 | Work in progress | Thaliparamba WS Dn EE | |
05 Oct 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
04 Oct 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
03 Oct 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
01 Oct 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
30 Sep 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
28 Sep 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
27 Sep 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
26 Sep 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
25 Sep 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE |