20 Mar 2021 DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS Nattika Project Dn AE 4
18 Mar 2021 DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS Nattika Project Dn AE 4
17 Mar 2021 DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS Nattika Project Dn AE 4
15 Mar 2021 DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS Nattika Project Dn AE 4
12 Mar 2021 DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS Nattika Project Dn AE 4
12 Mar 2021 DER submitted to WRD for obtaining revised AS on 21.01.2021. Awaiting for revised AS. Nattika Project Dn AE 4
08 Mar 2021 DER submitted to WRD for obtaining revised AS on 21.01.2021. Awaiting for revised AS. Nattika Project Dn AE 4
25 Feb 2021 DER submitted to WRD for obtaining revised AS on 21.01.2021. Awaiting for revised AS. Nattika Project Dn AE 4
24 Feb 2021 Land acquisition procedure is in final stage. form 11(1) published. DER and variation statement submitted for revised AS. Nattika Project Dn AE 4
24 Feb 2021 Land acquisition procedure is in final stage. form 11(1) published. DER submitted for revised AS. Nattika Project Dn AE 4