Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
27 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
26 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
25 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
24 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
23 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
22 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 -TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
21 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
20 Jun 2024 package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. Nattika Project Dn AE 4
24 Jun 2024 Package 1 -TS obtained.Applied in KIIFB. Package 2&3 TS obtained. KIIFB approval obtained.Package 4 Estimation ongoing Nattika Project Dn EE