| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 27 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 26 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 25 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 24 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 23 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 22 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 -TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 21 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 20 Jun 2024 | package 1- TS obtained,Applied in KIIFB . Package 2&3 TS obtained ,KIIFB approval obtained. Package 4 - Estimate is submitted for approval. | Nattika Project Dn AE 4 | |
| 24 Jun 2024 | Package 1 -TS obtained.Applied in KIIFB. Package 2&3 TS obtained. KIIFB approval obtained.Package 4 Estimation ongoing | Nattika Project Dn EE |