| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Sep 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 02 Sep 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 28 Aug 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 23 Aug 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 09 Aug 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 01 Aug 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 27 Jul 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 23 Jul 2021 | To be retendered after updation in PRICE | Perlassery Sn 2 AE | |
| 19 Jul 2021 | To be retendered after updation in PRICE | Kannur PH Dn EE | |
| 09 Jul 2021 | NO RESPONSE TO RETENDERS | Perlassery Sn 2 AE |