Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Nov 2021 TS approved and notice inviting for Tender Alappuzha Project Dn AE4
10 Aug 2021 Estimate for TS for length of RWPM 5700 m Reach I for amount available in the present AS has been submitted to CE Alappuzha Project Dn AE4
12 Jun 2021 Estimate for TS for length of RWPM 5700 m Reach I for amount available in the present AS has been submitted to CE Alappuzha Project Dn AE4
10 Jun 2021 Estimate for TS for length of RWPM 5700 m Reach I for amount available in the present AS has been submitted to CE Alappuzha Project Dn AE4
07 Jun 2021 The deviation proposal for pipe material from 900 mm HDPE to 800 mm MS spirally welded has been approved by TM. Now the estimate for TS is under preparation for the available AS amount. Alappuzha Project Dn AE4
01 Jun 2021 Raw water pumping main 9km from Mullaserikadavu intake to Pallipad WTP with 900 mm HDPE pipe in original proposal is required to deviated as directed 5/1/2020.A deviation proposal for pipe material with 800mm MS pipe was submitted to HO and awaiting approval. Alappuzha Project Dn AE4
18 Apr 2021 Construction of Intake chamber in progress. Bottom plugging of well is in progress. Reinforcement for bottom sealing in progress Alappuzha Project Dn AE4
14 Apr 2021 Construction of Intake chamber in progress. Bottom plugging of well is in progress. Reinforcement for bottom sealing in progress Alappuzha Project Dn AE4
09 Apr 2021 Raw water pumping main 9km from Mullaserikadavu intake to Pallipad WTP with 900 mm HDPE pipe in original proposal is required to deviated as directed 5/1/2020.A deviation proposal for pipe material with 800mm MS pipe was submitted to HO and awaiting approval. Alappuzha Project Dn AE4
09 Apr 2021 Construction of Intake chamber in progress. Bottom plugging of well is in progress Alappuzha Project Dn AE4