Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Jun 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
02 Jun 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
21 May 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
17 May 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
13 May 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
04 May 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
28 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
23 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
18 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
08 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE |