Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2023 | 500 mm DI K9 5478m supplied and 2005m laid | Mattannur Project Sn 2 AE | |
04 Aug 2022 | 400 mm DI K9 3473.5m pipe supplied and 3000m laid, 500 mm DI K9 5478m supplied and 820 m laid | Mattannur Project Sn 2 AE | |
20 May 2022 | 400 mm DI K9 1510 m pipe supplied and 749 m pipe laid | Mattannur Project Sn 2 AE |