Status Date Overall Project Status Project Officer Contact
08 May 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
22 Apr 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
19 Apr 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
16 Apr 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
11 Apr 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
06 Apr 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
20 Mar 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
21 Feb 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
12 Feb 2024 AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alappuzha municipality 6,9 - work completed final bill under process Alappuzha Project Dn PM
12 Feb 2024 work completed final bill under process Alappuzha Project Dn PM