Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Aug 2022 Work terminated vide ref. no. PHC/CHN/JNR/AMRUT/4421/2017 dated. 26.08.2022. Kochi JNURM Projects AE-6
19 Aug 2022 Column reinforcement work on progress. Kochi JNURM Projects AE-6
16 Aug 2022 No progress in work since last two months. The contractor neither submitted the programme chart nor executed the agreement as per the minutes of the meeting by Hon'ble Minister. Hence final notice had been issued by The SE,P.H Circle Kochi on 08/08/22. Kochi Project -AEE 3
06 Aug 2022 No work at site. Kochi JNURM Projects AE-6
03 Jul 2022 The contractor had been given a programme chart , directed to restart the work immediately and complete the work by 31/12/22 as per the decision in the Honble Minister's meeting.Extension of time was granted by SE,PH Circle ,Kochi and the contractor had been directed to execute the agreement.But so far contractor has not turned up to execute agreement or restart the work. Kochi Project -AEE 3
13 Jun 2022 Balance work is to be arranged at the risk and cost. Kochi JNURM Projects AE-6
30 May 2022 Meeting Fixed at Ministers Chamber on 3rd June 2022 Kochi JNURM Projects AE-6
24 May 2022 The estimate is sanctioned by CE and directed to SE for arranging the work as per rules. Kochi JNURM Projects AE-6
17 May 2022 TS approved by CE. Kochi JNURM Projects AE-6
11 May 2022 The estimate is resubmitted after making the corrections suggested by CE and estimate under scrutiny at CE office. Kochi JNURM Projects AE-6