Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 May 2023 | Work transferred to project division kochi 11 vide letter no. PHC/CHN/AMRUT/3578/2015/VOL 111 dtd 06.05.2023 of SE, PH circle kochi | Kochi WS Dn EE | |
17 May 2023 | estimate under verification | Kalamassery Sn AE | |
10 May 2023 | estimate under verification | Kalamassery Sn AE | |
09 May 2023 | estimate under verification | Kalamassery Sn AE | |
04 May 2023 | estimate under verification | Kalamassery Sn AE | |
02 May 2023 | estimate under verification | Kalamassery Sn AE | |
26 Apr 2023 | estimate under verification | Kalamassery Sn AE | |
24 Apr 2023 | estimate under verification | Kochi WS Dn EE | |
18 Apr 2023 | estimate under verification | Kochi WS Dn EE | |
10 Apr 2023 | estimate under verification | Kalamassery Sn AE |