12 Feb 2024 10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted Thaliparamba WS Dn EE
08 Jan 2024 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed Thaliparamba WS Dn EE
08 Jan 2024 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed Thaliparamba WS Dn EE
10 Dec 2023 1341 FHTCs out of 3080 FHTCs completed. 6 km of distribution pipeline laying completed and Interconnection wroks going on. CC IIIrd & part bill prepared and under scrutiny. Kalliassery W S Section - AE
09 Dec 2023 1157 FHTCs completed. Pipe laying 95% completed. 3rd and part bill submitted and is under scrutiny Thaliparamba WS Dn EE
09 Nov 2023 Work started, 731 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted Thaliparamba WS Dn EE
19 Oct 2023 Work started, 520 FHTC out of 3080 FHTC completed. CC II & part bill submitted Kalliassery W S Section - AE
14 Jul 2023 Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed and 80 geotagged Thaliparamba WS Dn EE
05 Jun 2023 Work started. PVC pipes for laying distribution line supplied. 50 FHTC out of 3080 FHTC completed in field. Kalliassery W S Section - AE
04 May 2023 Work order issued, Agreement executed, site handed over Thaliparamba WS Dn EE