Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Feb 2024 | 10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted | Thaliparamba WS Dn EE | |
08 Jan 2024 | 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed | Thaliparamba WS Dn EE | |
08 Jan 2024 | 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed | Thaliparamba WS Dn EE | |
10 Dec 2023 | 1341 FHTCs out of 3080 FHTCs completed. 6 km of distribution pipeline laying completed and Interconnection wroks going on. CC IIIrd & part bill prepared and under scrutiny. | Kalliassery W S Section - AE | |
09 Dec 2023 | 1157 FHTCs completed. Pipe laying 95% completed. 3rd and part bill submitted and is under scrutiny | Thaliparamba WS Dn EE | |
09 Nov 2023 | Work started, 731 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted | Thaliparamba WS Dn EE | |
19 Oct 2023 | Work started, 520 FHTC out of 3080 FHTC completed. CC II & part bill submitted | Kalliassery W S Section - AE | |
14 Jul 2023 | Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed and 80 geotagged | Thaliparamba WS Dn EE | |
05 Jun 2023 | Work started. PVC pipes for laying distribution line supplied. 50 FHTC out of 3080 FHTC completed in field. | Kalliassery W S Section - AE | |
04 May 2023 | Work order issued, Agreement executed, site handed over | Thaliparamba WS Dn EE |