Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Sep 2023 | Bill submitted to subdivision on 25.09.23 | Vytilla Section AE - 2 | |
21 Sep 2023 | Bill under preparation | Vytilla Section AE - 2 | |
15 Sep 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
08 Sep 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
05 Sep 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
01 Sep 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
24 Aug 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
04 Aug 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
01 Aug 2023 | Work completed. Bill under preparation | Vytilla Section AE - 2 | |
14 Jul 2023 | Road restoration work in progress | Vytilla Section AE - 2 |